Tuesday, April 21, 2009

Mid-tier alcove bridge

Not much new to report. I've started building the plywood subroadbed for the rest of the middle tier of staging. Just one picture to add:


Previously I mentioned that there is a 3' 9" wide alcove that the staging tracks have to span without supports because I will later want to be able to crawl under the track to get into the alcove. In that previous post I had a side picture of the upper tier alcove bridge. This picture above shows the underneath of the middle tier alcove bridge before it has been installed, so provides a better view of the bridge construction. (Note that the bridge is temporarily resting upside down on another part of staging -- this is not where it will be installed.)

There's not much to this construction. Two L-girders are attached together with nuts and bolts to provide a level surface, then the L-girders are attached to the underside of the plywood with #8 metal screws and washers. The plywood is strong enough to hold a whole slew of N-scale trains but it will tend to warp/bow unless something keeps it flat and level -- the L-girders provide that service and also provide some vertical strength in case some doofus like me stumbles and lands on the bridge.

Next step is to finish the subroadbed and add the blue roadbed -- I can complete both tomorrow if I can get a free hour to work on it.

Sunday, April 19, 2009

Upper Tier completed

Here's a picture of the upper tier with all track in place and tested. There is even a test train on the track:


One note about this construction is that I've made some improvements in the track installation techique. I learned, during the prepping of the Atlas switches, to file down rough edges in the switch rails that can catch wheels and cause derailments. Having done that procedure now for 24 switches I automatically paid more attention to the rail joints in this new section of construction, using the diamond files and even the rotary tool to make all rail connections super smooth. During testing I found that the newly installed track resulted in very smooth operations -- even better than what I found on the previously installed track. At some point I'll go back and apply those lessons to the rest of the staging track.

The only other construction note is that I compromised a bit on the wiring standards. The most recent construction consisted entirely of track re-used from the first staging attempt, usually in groups of 2 or 3 track sections soldered together and with the original feeder wires intact. As a result, I ended up with a few single sections of track with no feeder wire. Instead of adding an extra pair of feeders I just soldered these to one of the adjacent track sections. Throughout this process I've been using the multi-meter to test for shorts and I've found that there is virtually no resistance between adjacent rails soldered together, so I expect no troubles with this compromise. In fact, I'm beginning to think that my feeder-to-every-other-rail-joiner stategy may be overkill.

Once everything was completed, cleaned, and tested with the DC SD90MAC locomotive I hooked up the Digitrax and tested a long train on both grades. Here's a picture from part of that test:


The train in question is 33 Athearn Bethgon Coalporters, which are harder to pull than most other cars due both to weight and higher resistance wheels. With the two locomotives this train is almost 13' long -- over 2000' scale feet -- and would justify two or three lead engines in normal operation.

I found that two Kato diesels (SD40-2, latest release) pulled this up the 0.9% approach grade (the upper tier staging entry track near the wall) without any noticable affect on speed. Just for grins I tested the same train up the short 3.5% grade in the upper tier staging yard (as shown in the photo) and they got up just fine, albeit with some speed degradation.

Alas, when I tried two Atlas diesels (SD60M) they struggled mightily with just the 0.9% grade, making slow progress at full throttle and lots of wheel spinning.

This matches my previous experience with Kato and Atlas diesels from my 2002 test layout, although at the time I attributed the difference to the fact that the Atlas diesels I had then being only 4 axle (dash-8s) versus the 6 axle Katos (C44-9W). But, the Atlas SD60M also has that problem and it has 6 axles. Fortunately, most of my mainline modern freight diesels are Kato (17) versus only 4 for Atlas. For now I'll stick with Kato until I do some research and see if the Atlas problem can be solved easily. If not I can get by with assigning the Atlas engines to lighter duty work.

Finally, a note about time -- mostly because when I re-read these posts later I'll wonder why it took 3 weeks to finish the last section of the upper tier. My last post on upper tier construction was on March 28. One factor is that there was a lot of work required in this small space. 8 switches, reusing already soldered track, and fitting a lot of track into a conjested space all required extra time and attention. But the main factor is that I didn't have a lot of time the past 3 weeks due to lots of work at work and at home (prepping for 2 birthdays, Easter, some financial matters including the IRS, and several snowstorms that required driveway attention).

I may get more free time in coming weeks, but as the (hopefully) last Spring snow melts the outdoors is beckoning -- first the spring thinning of our little patch of forest, then the outdoor railway, which will generate a few posts of its own. I resolve to keep making weekly progress on the N scale layout, however. The next step is the middle tier of staging.

Monday, April 13, 2009

(not so) Secret Codes

In past posts I've mentioned Code 80 and Code 55 track. In model railroading, "Code xx" simply means the height of the rail above the top of the ties (a.k.a. "sleepers" in the British Commonwealth) in thousandths of an inch. For example: Code 80 track has 0.080" high rails.

"Why should I care about rail height?", you may ask. And many model railroaders happily build their layouts without ever worrying about rail height. However, it's just one more aspect of realism that a modeler may or may not be concerned about.

The problem is that most model train track has rails that are ridiculously big, and although most people don't notice at first glance, if you are looking at a detailed model of a railroad scene the oversize rail can often ruin the illusion.

In the prototype (a.k.a. "real life"), modern rails in the U.S. tend to all share the same flat-bottomed profile, as shown at the link. However, rail sizes can vary greatly. By convention, the rail size metric used is "pounds per yard" of rail. At one extreme, the early DRG narrow gauge lines used 30 lb. rail -- which is about 3 1/8" in height. At the other extreme the Pennsylvania Railroad (PRR) once used 155 lb rail for their main lines -- the heaviest rail in common use, and about 8" in height. Modern class 1 (the busiest main lines) rail tends to be in the 100-132 lb range (6-7 1/8" high), although some heavier rail (140 lb) is starting to be used. It's typical for a railroad to mix rail sizes -- sidings, spurs, branches and yards often have smaller rail -- often 80-90 lb or less.

How does that compare to the model? Well, in N (1:160) scale Code 80 was long the N scale standard, and is still the most commonly used rail. Code 80 is equivalent to over 13" high rail -- about double the size of a modern main line. Code 55 is now the preferred rail for N scalers more interested in the details, but even that translates to 8.8" rail height -- bigger even than the PRR. Code 40 track is available for those that want absolute accuracy, as code 40 is equivalent to about 6.4" high track (roughly 110 lbs/yard), but if you use code 40 you have to hand build your own switches. Some modelers choose code 55 for the main lines and code 40 for spurs and sidings.

How much difference does it make? Well, compare a photo of a prototype locomotive to its N scale equivalent sitting on code 80 track and you'll notice the difference right away -- of course, that's probably because you'll be looking for it. In practice, most people don't notice, especially if you "weather" your track by painting a rust color on the sides of the rails and do a good job with the ties and ballast. I have heard from one N-trak modeler who often takes his N-trak modules to conventions and he reports that no one noticed (or at least no one commented) when he converted to code 55 from code 80. However, he gets lots of comments when he makes other changes to the details.

Still, I am using code 55 on my main layout, in large part because code 55 track products look a lot better overall, not just the rail height, than do the code 60, 70 and 80 N scale products.

For the record, the reason N scale track manufacturers initially chose code 80 was operations reliability. As with all model train scales, oversize rail and wheel flanges were chosen to minimize derailments. Today, modern plastic and metal manufacturing techniques are much more precise than they were in the past, so we can acheive even better operational reliability without the oversized rails and flanges. Even so, there are potential operational issues with certain brands of N scale code 55 track, and I'll cover that in a later post on track brands.

For those interested in more details on rail heights and sizes in the prototype and in the model scales, here is a good site.

For those interested in very high accuracy model railroading, what is commonly called "fine scale" modeling, the Proto 87 site is worth a visit. The term "Proto 87" simply means trying to precisely and accurately model the prototype in HO (1:87) scale. In addition to getting the rail size right, they also try to model exact replicas of (for example) switches and wheel flanges. This type of modeling is not for everyone, as there is a lot of extra effort required. But its a lot of fun to look at the results of a successful Proto87 modeler.

Monday, April 6, 2009

Outdoor model train scales

In the earlier post on gauge and scale I mentioned that the "large", outdoor scales range in size from 1:20.3 to 1:32. While these may seem like random numbers, there is a very logical reason behind them, dating back to the early history of model trains.

Some of the earliest model trains in the late 1800s were made by Märklin in Germany. They built three sizes of trains and named them "1", "2", and "3" gauge. All three were on the large size, reflecting the technology at the time. "1" gauge is 45 mm between the rails, about 1.77 inches.

When Lionel started making electric toy trains in the early 1900s in the U.S. they decided to name their gauge "0", pronounced "zero", because it was somewhat smaller than "1" gauge. However, people reading "0" (zero) thought it was the letter "oh", and so "O" has forever been the name of 1:48 scale. The smaller O scale trains quickly surpassed the larger 1 gauge trains in popularity because they took up less space. While "1" gauge trains continued to be produced in smaller quanitities, "2" and "3" stopped being produced.

Later in the 1930s Märklin came out with an even smaller scale, 1:87, and named it "half-oh", or "HO" for short (even though it was quite a bit bigger than half of 1:48). HO quickly leaped ahead of O in popularity, as many other manufacturers followed Märklin's lead. "1" became an almost forgotten gauge.

Fast forward to the late 1960s when a family named Lehman in Germany decided to build electric trains that could run outdoors. They chose "1" gauge track and named their new company LGB for Lehman Gross Bahn -- which translates literally to "Lehman Large Trains". For their initial line of trains they chose to model European prototypes that used a 1 meter narrow gauge. A 45 mm gauge track, when used to model a meter gauge prototype, yields a scale of 1:22.5. This soon became known informally as "G" scale. However, "G" was never officially recognized as a scale, and today people often mistakenly use the term "G" for any train running on "1" gauge track.

LGB trains were a hit, first in Europe and then in the states. In the 1970s LGB introduced more trains, including models of standard gauge European trains and 3-foot narrow gauge U.S. trains. LGB was vague about the scale of these new models, in part so that the cars from one size prototype wouldn't look out of place in the same train with others, and this resulted in a lot of confusion. (Today some modelers feel that LGB's failure to provide accurate scale info with their models ultimately contributed to their sales decline and their recent bankruptcy.)

In the 1990s and 2000s many other manufacturers entered the large scale train market and fortunately almost all of them provided specific scale info. For "1" gauge models based on a 3-foot U.S. narrow gauge prototype the scale of 1:20.3 is correct. The NMRA has recognized this as "F" scale . For "1" gauge models based on standard gauge the correct scale is 1:32, which is now recognized as "H" scale. It's easy to remember these letters because F-G-H are all "1" gauge scales, based on 3 ft gauge, 1 meter gauge, and standard gauge prototypes respectively.

Unfortunately, before H scale was established Aristocraft introduced a line of "1" gauge products based on standard gauge prototypes in 1:29 scale. As such the trains were somewhat larger than they should be given the wheelbase of the trains. Aristocraft chose 1:29 apparently because this allowed the LGB narrow gauge boxcars to look correctly proportioned next to Aristocraft product. USA Trains copied this practice, and their product line became very popular due to their lower prices and US prototypes, so other manufacturers followed their lead. Today large scale modelers now have to be aware that some standard gauge product is 1:29 scale and some is 1:32, and to try not to mix them because they will look funny together if you do.

Just to complete the confusion, a lot of the non-train models that are available for adding scenery to your outdoor layout are 1:24 scale, which kinda-sorta works with some of the other scales if you don't look too closely, or if you separate the 1:24 models from the trains visually.

One other point to note is that although all the "1" gauge trains will run on the same track, there are still separate lines of F, G, and H scale track. That's because while the rail gauge is the same, tie sizes vary greatly between scales.

Now, having said all of the above its worth noting that Garden railroaders tend to be a lot more relaxed than indoor modelers about prototypical accuracy. Many happily run trains of mixed scales. Others may run all their narrow gauge trains one day and all their standard gauge the next. And despite such sacreligious behavior they amazingly still get their layouts featured in Garden Railway magazine! :)

For my outdoor layout I have chosen a U.S. 3 foot narrow gauge prototype, so my scale is F (1:20.3). Actually, to be precise, my scale is Fn3, reflecting the 3 foot narrow gauge. However, the "n3" is usually not mentioned since virtually everyone in F scale is doing narrow gauge.

Sunday, April 5, 2009

Design influences: third layout

I started my 3rd layout late in 1989, almost 9 years after my second layout was built and dismantled. I was newly married, and my wife, noting my intense interest in both real and model trains, suggested I build a layout. I immediately adopted her suggestion, of course, as I did not want to be disagreeable early in our marriage. ;)

Popular layout design theory holds that there are three decisions you need to make before you get started designing the layout: theme, scale and site, though not necessarily in that order. For my third layout the theme was a given -- European passenger trains. I'd moved to central Germany in 1987 and had traveled western Europe extensively for work and tourism while I was there. Europe had, and still has, a plethora of wonderful passenger rail. Furthermore, shops with European model trains were plentiful, with virtually one in every decent sized shopping district plus large model train departments in most of the big department stores. In 1989 I had one of each within 3 blocks of my apartment. Given that I was in the center of all this, and that I loved passenger trains, no other option was even considered.

As to scale, I was predisposed to HO but had to do some research before deciding. I visited a couple of local shops and found that German model trains were different in many ways from those in the U.S. In the U.S., with the special exception of Lionel Toy Trains, a wide variety of manufacturers will make interoperable equipment for the same scale. In Germany, at least back in 1989, modelers tended to stick predominantly to one manufacturer. I think this was mostly because the largest manufacturer, Märklin, set the tone with their distinct HO product line. Märklin HO has proprietary couplers and a unique 3-rail track system, with the third "rail" fairly well disguised as metal bumps in the center of the ties.

So the first question the train shop owners asked me was "which brand of model train are you using?" I hadn't decided, so in response I reviewed a few product catalogues and settled pretty quickly on Märklin HO. I suppose part of my rationale was the apparent quality of their product and the relative breadth of the their product line. But the main reason was that in 1988 Märklin had introduced their "Digital" line, which was what we now know as DCC. Such a product rollout was and example of the key advantage of a proprietary model train brand. While the rest of the model train industry would spend the next 15 years or so evolving the standards and practices to make DCC practical and universal, Märklin was able to provide all the necessary components all at once, out of the box. No messy decoder installs or debugging of weird timing problems between different manufacturers. It was literally plug-and play back in 1988.

Having decided on theme and scale I now needed to pick a site, and that was a bit of a challenge. We lived in a 61 square meter, one-bedroom apartment. Not small for two people, but not very accomodating for a model railroad. I knew the layout would need to be portable in sections, both because we would eventually move out of the apartment, and also because I would need to put it away in the storage locker when we entertained. I eventually settled on a 3x1 meter portable layout concept consisting of three 1x1 meter sections. This is roughly 32 square feet -- about the same as an American 4x8 layout, but somewhat longer and narrower.

With theme, scale and site decided I then needed a layout design. I quickly found that it was going to be very difficult to squeeze an interesting passenger layout into such a small space. When you start any layout design it's helpful to figure out the key constraints and requirements at the start, what the great layout designer John Armstrong called "Givens and Druthers". For me they were:

  1. Train length. I wanted to run trains of up to 5 passenger cars. The longest train measured 160cm with the locomotive.

  2. Curve radius. It was a given that any curves were going to be of the tightest possible operational radius, and hidden in tunnels because they would look so unrealistic. This turned out to be about 40cm radius if I recall correctly, or about 15".

  3. Stations. Passenger train layouts need stations. At first I was open to a minimum of one station, either a through style or a stub terminal style. After sketching a few designs, though, I realized that I needed a minimum of two stations to keep it interesting, and ideally one of each style.

  4. Realism. The setting should be at least possible, if not plausible. This implies that the trains would need to exit through a tunnel somewhere to go "off stage", which would represent the "rest of the world". I had not heard the term "staging" back then, but the requirement for staging was clear. It also meant that oval designs or twice-through-the-same scene designs were out of the question.
I sketched all kind of layouts but just couldn't find a solution that I liked. The best I could come up with was a layout with a 3-meter-long view block lengthwise down the middle. On one side would be the stub terminal, then the train would go through a curved tunnel to the other side where there would be a through tunnel. Then the train would go through another curved tunnel to an under-layout staging area.

But this design concept had at least three problems. First, the overall run for the train was very short, making it less interesting to operate. Second, there was the problem that trains would still be exiting the first station while simultaneously entering the second. Finally, this design requires walking around the layout to follow the train, which is acceptable in theory, but in practice is difficult given that Märklin did not yet have walk-around controls.

I bought some German layout books seeking inspiration, but found no answers. I dug out my old copy of the "101 Track Plans" book that I used for my second layout, but still nothing satisfied. I eventually got so frustrated that I seriously considered switching to N scale, even sketching some N scale plans for the same space. Finally I found my solution by looking "one last time" at a Märklin layout design book. Most of the Märklin layouts in that book eschewed realistic operations, but one design stood out:


To see why I liked this, ignore the logging and industrial elements in this picture and focus just on the layout of the main line. The railroad starts at the stub terminal at the top of drawing, which is at the top of the hill, then winds its way down slope, making two horseshoe turns with the second turn in a tunnel, and arrives at a through station. From there it goes into a tunnel that goes to "the rest of the world", a.k.a. "under layout staging".

I might not have seen the passenger possiblities here if my wife and I had not been making frequent visits to Switzerland, where I'd noted the following about Swiss mountain railroads: 1) The Swiss have a lot of tunnels, and often in places where Americans would have chosen a large cut; 2) There are a few mountain towns in Switzerland that are accessible only by train or hiking path; 3) There are some places where two stations are quite near each other, separated as much by elevation as by horizontal distance; and 4) compacted, complex trackwork is common throughout the Swiss mountains as they often have to squeeze track into small spaces.

So, I could see this track layout working with a Swiss mountain theme. The track distance between the two stations allows for a longer run that addresses the concerns stated earlier. The two stations would be separated mostly by elevation and in a mountain town that was accessible only by train. I would not include the industry shown on the Märklin drawing, but would allow a "goods track" at each station for local freight deliveries (what in America we would call a "team track"). For even more fun the theme would be a ski village in winter. And the whole layout could be viewed and operated from one side.

The next step was to compress the layout design from the 3.0x1.7 meter space shown in the drawing to my 3x1 meter space. This wasn't hard as I didn't need the space that was set aside for industry. As I drew the detailed design it I re-routed the main line and made a few changes, most significantly adding a turntable to the stub terminal. This was totally non-realistic as the Swiss converted to electrical railroads for their mountain tunnel lines very, very early (the first decade of the 1900s I believe), but I wanted the flexibility of running steam. I later gave the railroad a specific date of Boxing Day (day after Christmas), 1956, and planned to string electric catenary. The idea was that the catenary would be new, so new that the viewer couldn't tell whether it was yet operational. I could then run steam, diesel or electric depending on my whim.

I built the layout in early 1990 using a German language model railroad how-to book as a guide. The methodology they used worked, but I don't recommend it because it's not very conducive to later revisions of the layout. The Märklin turntable I'd included in the layout plans was announced but would not be available until 1992, so I ran trains without it for the first year. The digital system worked great, and I built a few models and a bit of scenery.

By 1991 I just left the layout in the storage locker, as moving it in and out had become a pain. In late 1991 I took a job in California, and in early 1992 we moved into a new house. The layout was setup in one of the bedrooms. This picture shows it shortly after things were unpacked and I had gotten the trains running:


Unfortunately, this amazingly is the only photo I have of the layout today. Alas, the angle is not good for seeing the track plan, the scenery is not in position, and there are even random items piled on the layout in places. I think I took this picture as part of a series showing each room in the house after move-in. Furthermore, the turntable was not yet in place. However, as it is the only photo I have I'll have to use it to describe the layout, and how it differed from the Märklin drawing that inspired it.

The top tier was the stub terminal -- this level had no slope. There were three tracks for passenger trains and one short track, on the side farthest from the camera, for goods cars. The space for the turntable and a few locomotive tracks was on the right -- I would add the turntable to the layout later in 1992. Two double-slip switches connected the turntable to the passenger tracks. There was an escape crossover near the end of the two longest passenger tracks, to allow for backing steam locomotives back to the turntable, turning them, and attaching them to the other end of the train for the return journey.

The middle tier was on a 4-5% grade connecting the two stations, with the left half of this tier in a tunnel. I added a siding to the middle tier between the curves, and this proved very useful in operations. The inspiration for adding a siding partially in a tunnel came from the line between Grindlewald and Wengen in Switzerland.

The lower tier was on a 1-2% grade with a two-track through terminal. A short goods track was also included on the left side. Curved Märklin switches were used at both sides of the lower tier so that the station tracks were long enough to accomodate the passenger trains.

The underneath staging level consisted of a double-track reverse loop. Because of Märklin's 3-rail system no auto-reverse mechanism was needed. Staging could accomodate up to 4 trains.

Operations consisted of a tight holiday schedule of regional, local, and worker passenger trains, with two runs for goods cars placed at gaps in the schedule. To add operational interest special events, such as late trains or a non-functioning engine, were introduced at random intervals.

I continued to run trains and enhance the layout occasionally through the end of 1993, when our first child, Paige, was born. During that time I'd converted the layout from being in 3 sections to one large section, in order to make continuing construction easier. Work then essentially stopped on the layout until late 1995, when the arrival of our second child, Daniel, meant the layout had to move into storage. I built a special holding platform for it high in the garage and packed it all away as carefully as I could, and it sat there for many years.

In early 2002 I found that my train-obsessed son was climbing up a ladder in the garage, lifting the layout dust cover, and spending hours staring at the the layout. He had his own HO trains (supplemented by my old American HO trains that had been converted with modern couplers) on an oval layout on a flat board. But he was fascinated by the mountain layout with the slopes and bridges. We decided to swap the two layouts -- the Märklin one went in the garage spot where his had been, and his went where the Märklin one had been stored. We then revived the Märklin layout and ran trains for several months.

It all ended when I decided to start a new layout in N scale. The Märklin layout went back into storage and was dismantled for our move in 2005. I have a tinge of regret about that, but I'd realized that I never was going to have time to finish the Märklin layout given a) my new interests in N scale and large scale and b) that I'd lost interest in Märklin 3-rail.

So, what were the lessons learned from the 3rd layout?

  1. Yes, I love passenger trains. More specifically, I loved the drama of the trains coming in and out of the stub terminal and crossing over the double-slip switches. The stub terminal was my favorite part of the layout, especially with the abundance of operational possibilities after the turntable was added.
  2. Double track is cool. This layout was single track operationally, although with two stations and a siding most of the actual main route was double track. I did this because single track is recommended for layouts because it increases operations activity due to having to accomodate meets between trains in opposite directions. But as I looked at the staging part of the layout, with the double-track curve, there was something about that "boulevard of steel" that made me want to emulate that on the main line with my next layout.
  3. Digital is cool. Märklin digital, less so. For one it's ridiculously expensive, and for another many of the operations were very difficult due to limitations of Märklin controls.
  4. I can do without turntables. Oh, they are fun and cool to look at, but the huge amount of work required makes me question the fun/work ratio. I haven't planned one since, although my outdoor layout will probably have two for prototype reasons.
  5. I'm ready for a really big layout. After this layout was done I felt I'd done as much as I could with small space compromises, and that what I really wanted were long trains over very long runs and curves that weren't so tight that they had to be hidden in tunnels.
  6. I want more realism than what this layout offered. Given the space I had it was the best I could do, but some of the pretenses required to create interesting operations were really stretching the term "realistic". Another reason to go big with the next layout.
  7. I discovered that my modeling interests tend to be influenced heavily by where I live. When I built this layout I was surrounded by European trains and couldn't imagine modeling anything else. I think that part of the reason my interest waned in 1994, apart from the thrill of a baby in the house, was that European trains were becoming a distant memory to me -- and when I revived the layout in 2002 the European trains seemed no more realistic to me than the Thomas the Tank Engine trains my kids had. However, at that same time I'd become very interested in local railroads like the Southern Pacific and the old narrow gauge South Pacific Coast.

All of these lessons would factor into my current layout. Unfortunately, in 2002 I still didn't have the space to go "big", so my 4th layout would have to incorporate some, but not all, of these learnings.

Saturday, April 4, 2009

Gauge vs. Scale

In model train conversations it's common to hear the terms "gauge" and "scale" used interchangeably, as in "HO gauge" as a synonym for "HO scale". This is especially true for model railroading newcomers. While this causes no harm, as everyone understands what is being said, the two terms have different meanings:

Scale -- The size of the model relative to the prototype.

Gauge -- The distance between the two rails.

For example, N scale is 1:160, which means it is 160th the size of the prototype. If a prototype freight car is 80 feet long, in N scale it would be 160th of that, or 1/2 of a foot long.

In terms of gauge, prototype standard gauge is 4 ft 8.5 in between the rails, which translates to 9 mm between the rails in N scale. ("N" was chosen for the name of 1:160 scale because of the Nine mm rail gauge. )

So, if you say something is HO gauge what you are saying is that it is 1:87 (HO) scale and standard gauge. Similarly, the term "HOn3" means a model that is 1:87 scale, but representing a prototype narrow gauge of 3 feet. The "n3" of "HOn3" means: "narrow gauge, 3 feet". There is also an Nn3 -- 1:160 scale and a narrow gauge of 3 feet. Another popular example of modeling narrow gauge is On2.5 gauge -- which is O scale (1:48), narrow gauge of 2.5 feet.

The National Model Railroad Association (NMRA) has their own web page on scale and gauge which covers this topic in detail, including a list of scales common for indoor model railroads.

Although many model railroad scales have been established they clearly do not enjoy equal popularity. The most popular scale by far is HO, with N a distant (but growing) second, and the other scales further behind. TT scale (1:120) is virtually dead, killed off by the introduction of N in the 1960s. OO scale (1:76.2) is very popular -- perhaps the most popular -- in Britain but is almost unheard of elsewhere.

The NMRA web page I linked to does not, for some reason, list the "large" scales, from F (1:20.3) to H (1:32). These scales are commonly referred to as "outdoor" or "garden" railway scales because, although you can run them indoors, they are mostly used outdoors.

Sunday, March 29, 2009

Atlas Code 80 Switch Prep Procedures

Atlas Code 80 track and switches have seemingly been around forever, literally since the 1970s or 1960s. They are still sold today because they have one huge advantage: price. An Atlas Code 80 #6 remote switch, which includes a snap relay switch machine and a switch control box, can be bought for $13.35 at Brooklyn Locomotive Works. By comparison, the combined cost of the more widely preferred Atlas code 55 #7 switch with Tortoise switch machine and a typical SPST switch box will run you at least $25 -- and other options such as Peco or MicroEngineering switches are significantly more expensive even than that.

Of course there are reasons Atlas code 80 is so cheap. First, it doesn't look anything like prototype track. Second, functionally speaking the slow-motion switch machines are superior to the old snap-relay variety. And third, there are valid concerns with the Atlas code 80 switches' out-of-the-box reliability.

I use Atlas code 80 in staging because: 1) prototype-like looks aren't important in staging, and 2) with 73 switches combined in my 5 staging areas the cost savings are significant. This means I had to come up with a solution to address the Atlas code 80 switch reliability problems, and that's the topic of this post.

Here is a picture of an Atlas code 80 #6 switch in package next to one that has been prepped for the layout. I've added three circles at places on the prepped switch to help with the explanation of the prep procedures. To get a bigger view simply click on the picture:


As far as I know the procedures here will also work for Atlas' smaller #4 switches. However, I recommend #6's because they are longer, with a wider curve radius, and thus more likely to operate reliability with any N scale equipment.

One point worth noting is that Atlas has improved these switches many times over the decades. Most of the chronic problems that were documented in the 1980s, for example, have been addressed in the current version. The issues that remain are addressed in the steps below:
  1. Open the package. The switch controller and screws can be set aside until if/when you are ready to use them for switch control. The 6 rail joiners should be separated with a cutter, such as the Xuron rail cutter, and trimmed so that there is no excess metal on the ends of each joiner. I then put them in a rail joiner drawer until they are needed on the layout.

  2. Inspect the switch. Look for track out of alignment and test the switch machine manually. Use a truck, such as a Micro-Trains replacement truck, to see if it catches anywhere when run over the switch. Once you've followed these procedures with several switches you'll probably be able to see the problems areas by eye without testing.

  3. Look closely at the rails inside the red circle in the photo above. This is where the closing rails meet the point rails. I find it helpful to use a magnifying visor for this step. In almost all cases the closing rail is not in line with the point rail (the point rail is the one which moves), but instead sticks out a little. This "sticking out" can cause trucks to skip over the bump and in bad cases can lead to derailments. Using a small metal file gently file down the side and top of the closing rail end, and if necessary the end of the point rail as well, until the transition from one rail to the next is smooth. Note that this problem usually affects the diverging route but not the straight one, but just to be safe I file the rails for both routes.

  4. Now inspect the plastic frog inside the yellow circle in the photo above. In some cases the frog is too big and thus can cause wheels to bump up when they travel along the frog. The solution is to file down the top of the frog tip, then file the sides of the frog tip to assure that wheels pass by smoothly all the time.

  5. Check the ends of the point rails (shown inside the green circle in the photo). To be honest I've not seen a problem with these in the current generation of Atlas code 80 switches, but historically the point ends can be off level with the main rails. If so you'll need to add shims under the point rails or file down the rail tops as appropriate.

  6. Now test the switch machine. This can be done by wiring it up per the instructions on the back of the switch package. However, to save time you can take two wires, one black and one of another color, and briefly touch them to the accessory terminals on your DC power pack. Then do the same with the other color wire and the black wire. Test only once, to avoid overheating the switch machine. Again, I've not experienced any out-of-the-box problems with this generation of Atlas code 80 switch machines, but if a problem does arise I want to find it before I install the switch on the layout

  7. Finally, as the switch wires are short you'll probably need to extend them. I strip about 3/8" of insulation off each wire and crimp yellow butt splices (gauge 16-22, as shown in photo) that are found at Radio Shack. I don't add wire to the other side of the butt splice until the switch is on the layout, as until that time you won't know how much additional wire will be needed.
After that the switch is ready for the layout.

Saturday, March 28, 2009

Where to shop for N scale

[Update from the future (October 14, 2010): CharlestonDigitalTrains web site is now showing very low inventory, missing most of the items they used to carry. I'm now using Wig-Wag Trains for DCC stuff. Also, note that Wholesaletrains.com has great prices on Atlas flex track.]

One of the standard first questions that new N scalers ask is "where are the best places to shop". This post is my view as of today. There are a number of really good shops out there, so this list is certainly not complete. But every one of these shops have worked out well for me.

Wig-Wag Trains is a 99% N scale shop located in Albuquerque, NM. I buy the large majority of my N-scale-specific goods from them. Wig-Wag has some unique practices that can take getting used to, but once you are familiar with them you’ll find that they can both save you a lot of money and keep you on top of the latest N scale products well in advance of their release.

Wig-Wag posts their discount policy on a page linked to their main page, and for nearly everything their prices are at least equal to the best anywhere. One special part of their discount policy is that if you reserve a new product in advance – such as a future release of an engine or rolling stock – you get an additional discount that usually results in the best price available anywhere. And, to make planning easier, their News page is continually updated with the latest product announcements giving you plenty of time to send in reservations. I visit the News page at least once per day.

On the quirky side, though, is that Wig-Wag doesn’t have an automated on-line order system. You have to first call them to give your credit card info, then use email to send orders. This also means that if you have a lot of reservations you’ll probably find it helpful to keep track of them in a list somewhere. Wig-Wag is very good about sending the new product to you shortly after it arrives, and on the rare occasion when they make mistakes they are quick to correct them without argument. But still I find it helpful to know what's in the queue and to compare deliveries with what I expected.

The disadvantage of Wig-Wag is that they are so popular and have such a high volume of business that they are sometimes overwhelmed. Their email can get backed up – something that they’ll note on their News page – and responses can get slow. If I need something to be delivered right away I won’t use Wig-Wag because the turnaround time can be unpredictable.

Charleston Digital Trains is run by Mike Gleaton in South Carolina. He specializes in DCC and related products, such as switch machines, and I buy virtually all of my DCC/related stuff from him. There are three reasons for going to Mike: his prices are great (equal to the best on the web), his service is superb, and he’s extremely knowledgeable and helpful about his product area. He often posts answers to questions on various news groups. Sure, this helps advertise for his business, but his answers are free and correct.

Brooklyn Locomotive Works is, like Wig-Wag, an N-scale only (almost) dealer and apparently is the highest volume one in the U.S. I say this because Micro-Trains, an N- and Z-scale only manufacturer, lists BLW as their top dealer for 2008. I like Wig-Wag for the reasons given above but BLW is also extremely price competitive and offers great service. I’ve used them for a few things when Wig-Wag was out of stock, or when I needed an item immediately. They also have occasional sales on older items that beat anyone's prices anywhere. And for some reason they have significantly better prices than anyone on Atlas switches (but they have a large handling fee for track).

Tony’s Trains in Vermont may well be the original DCC-specialist vendor. Their web site is full of useful DCC information and they’ve even produced a few of their own products to meet special DCC needs. I ordered from them a few times before I discovered Charleston, and they seem excellent. I just prefer the personal, knowledgeable service I get from Mike Gleaton.

Those are the web sites I buy from these days. In addition, I occasionally make the trek to Denver for business or personal reasons, and if time allows I stop at Caboose Hobbies. Until recently their reputation was a “very big store with very big prices”. Recently they’ve dropped prices and are now more competitive, though still not on par with the best. They have an active web site, but I only buy from them in person.

This really is a huge store, with at least a dozen aisles at least 60-80’ long (I’m probably understating) and at least a half a dozen model railroads on exhibit. I swear they have at least 8, and probably a dozen, employees there at all times, even midweek, and I’ve never seen less than ten customers in the store at any time.

Their HO stock is massive. They also do a great job with large scale and O, and although their Z area is relatively small I think they have the whole Micro-Trains line. Their N scale area for locos, track, and rolling stock is on the small side. However their N scale modeling supply aisle is incredible.

In addition they have a tremendous selection of non-scale specific items, such as scenery and electrical tools, digital stuff, and especially books and magazines.

Caboose is the place I go when I want to see something before I buy it.

So, those are the current retailers I buy from. Below are a few I've bought from in the past, but don't anymore.

First, eBay. Yes, when you first get into N scale eBay seems like a great place to get stuff, and it is a good way to learn about what products have been released in the past few years. But, in practice it’s not much of a cost saver, if at all, when you consider the time you spend. Also, while at first eBay seems like a good way to get out of stock items, after you’ve been at this for a while you learn that any in-demand out-of-stock item will soon get re-released in a version that’s probably improved.

One example is the Proto 2000 2-8-8-2, which I bought from eBay in 2005. The early versions were not DCC Ready, so my DCC decoder install was especially challenging. I’ve run it only occasionally, so it would have been better if I’d waited for the 2007 version with decoder built in.

The other "shop" I’ll mention is Ye Olde Local Hobby Shop (LHS). Within the hobby there are many people who’ll assert it is your patriotic duty to buy from your LHS to keep them in business. And I can see that, within reason. For example, when we lived in the Kansas City area temporarily in 2005 I discovered Show Me Lines, one of America’s great LHSes. Sure, their discounts weren’t quite what you could get on the internet (20% was their standard), but the owner went out of his way: to help you; to make his shop a friendly place for your kids; and especially to promote the hobby locally. On that last point the owner was incredibly active with local clubs in all scales, and he was quick to tell any visitor about those clubs and welcome the visitor to join. I can see taking a slight price hit to support a shop like that.

Alas, there are 2 train shops within 30 minutes of our home, and neither is worth a second visit. (I’m not counting those "hobby" shops that include a tiny, overpriced, dusty train section apparently just for decoration.) Both of these local shops sell trains at list price, neither has much N or large scale, and on top of that the owner of the one closest to me is rude to his customers. No, that’s not the type of LHS I will support.

Electrical short debugging

As mentioned earlier today, I discovered an electrical short when testing the newly laid upper tier track. At the time I'd inspected the new track and feeders and didn't find the cause.

This evening I tried again. First I finally cut the rail between the upper tier Auto Reverse (AR) section and the main track. Once done I confirmed that the problem was with the main power district, not any of the three AR sections. Then I very closely inspected all the new track and feeders, including switches, and even moved wires around as a precaution, but still did not find the short.

At that point I began to suspect the track laid earlier for the lower and middle tier. I'd successfully tested that track at the time, but haven't run trains on it for over a month, so there is a decent chance that some of the adjacent construction activities could have caused a short. I cut the power bus wire between the I and J terminals in a way that will allow for easy reconnection. Then I tested and confirmed that the problem is with the older track.

At that point I tested the new track with the SD90/43MAC and everything worked great. The good news here is that all the precautions and applied lessons seem to be resulting in better trackwork, especially the switches.

The bad news is that I still have an electrical short on the old track. I inspected everywhere i could reach and removed several staples to look underneath but found nothing. I'll probably need to remove the upper tier bridge, and in order to do that I'll need to finish the rail cutting for the left side of the bridge.

Hopefully I can resolve tomorrow. If not I can continue work on the upper and middle tiers for at least a while before this electrical short blocks progress.

Diamond rail cutting

Ever since I completed the upper tier bridge structure I've had a "to-do" item of cutting the rails on both sides of the bridge in order to make it removable.

The challenge is that the rail gap must be wide enough to prevent electricity from passing across it, but narrow enough to allow the trains to pass smoothly across the gap. It is especially challenging in N scale to get a small enough gap because our wheels are so tiny. We can't use insulation to pad the bridge gaps, as we do the other rail gaps on the layout, because the bridge rails need to come up easily when the bridge is removed.

I tested a couple of thin-blade manual saws on some left over track and found them wanting: in part because it was hard to keep the saw from wandering off course and damaging the track surface; and in part because the back-and-forth saw motion created a lot of strain on the rest of the track.

Then I tested a rotary tool, commonly called by the name brand "Dremel", and it worked great. The only problem was that the resulting gap was too wide due to the width of the blade.

Today, while I was in Denver for other reasons, I dropped by Caboose Hobbies and found a thin Dremel diamond blade that looked to be perfect. It was $19 (yikes) but as no other solution is apparent, I bought it. After testing on a piece of scrap track I tried it on the track on the right side of the bridge:


The rail gap is so small in this picture that it is almost impossible to see. Look at the upper track, immediately to the right of the wooden bridge side. Below that track you can see the tools used -- the rotary tool with diamond blade, safety glasses (the blade really kicks up a lot of fine dust), and a simple box cutter I used to cut the plastic ties after the rail was cut.

The only problem was that after cutting it turned out that the track itself wasn't sufficently glued down on the right side of the cut. So, I added some glue (the white stuff at the bottom of the track in the photo) and used a pin to hold the track in place until dry.

Once dry I'll gently file the rail edges and test with a locomotive. If this works I will add the diamond blade to the track laying arsenal for special situations like this.

Wired .... but ...

20 pairs of feeder wire and 5 sets of switch machine wire, including the unwired one from the middle tier, have been completed, and the new track has been cleaned:


Alas, testing this morning found an electrical short somewhere in this picture. I've searched for the obvious causes with the newly installed wire, such as feeder wires reversed or broken wire insulation, and found nothing.

In the back of my mind I knew I should have been testing for shorts with the multi-meter as I made each wiring change -- but I didn't. Lesson learned. I will do so from now on.

When tracking down shorts the first step is to isolate parts of the circuit to narrow down the possible causes. Unfortunately, this is one big circuit except for the AR sections. (Hence the rational for power districts.) This may take some time to locate.

Thursday, March 26, 2009

Editing

Over the past couple weeks I've been editing the past posts in my spare time. The changes were mostly minor: improved some formatting and a little rewording. These changes reflect things I've learned through regular posting. I've also added Label words for each post, so searching for posts on a given topic will be streamlined.

Sunday, March 22, 2009

Weekend Update

Here's a picture of the layout as of Sunday evening:


The whole of the upper tier now has the blue roadbed in place and track has been laid up until where the north side switch ladder will be. The track has not had the feeder wires connected yet (all those black wires seemingly randomly placed above the layout are feeder wires that are connected to the track but not to the terminals).

In addition, you can't see it but in the past week I also: desoldered a bunch of the switches that were left over from the previous staging attempt; did some wiring work near/on the upper tier bridge (the feeder wires to the bridge track are now reached by disconnects to facilitate removing the bridge for maintenance); set up the Visio diagram for the upper tier; and began wiring the remaining switches on the south end of staging.

All in all, it was a good 4-5 hours work in the past week on the layout. Not as much as I'd like, but still making progress.

Nothing in the past week was particularly challenging -- just application of tried-and-true layout building techniques. My next step is to complete the wiring of this new track (including the south side switch machines), then clean and test it. Once that is done I'll finish up with the rest of the upper tier track.

I've begun shopping for the power cabinet components. That seems like a project that I may tackle before completing the middle and lower tiers of staging.

Monday, March 16, 2009

Design influences: Maps, Progressions, Prototypes, and Freelancing

For as long as I can remember I've had a fascination with maps. Road maps, topological, geological, panoramic, satellite -- you name it.

I love studing existing maps, but I've also loved drawing maps of imagined places. Some of these fantasy maps were quite involved and took literally months to complete. Usually I'd work on these in idle situations, such as listening to lectures in college or while on long plane flights.

My one driving interest in maps has always been the historical angle: how did things progress to where they are today? Every now and then I'll stumble across a book some like-minded soul created of the map history of a given area and I'll buy it and closely read every page.

This interest in maps, history, and progressions definitely influences my railroad design, although in different ways depending on whether the layout has a "prototype" or "freelance" theme:
  1. Prototype

    Model railroaders refer to a real railroad as a "prototype" and what we build as a model. So a prototype layout is one that attempts to duplicate a real railroad at a real time in history as closely as possible.

    For my outdoor layout I've chosen to model the Denver and Rio Grande circa 1884-5 between the cities of Salida and Leadville in Colorado. A love of maps is extremely helpful in creating this kind design because you'll need to conduct a ton of research -- including lots of maps -- from a variety of sources. Fortunately, the Colorado Railroad Museum in Golden and the Leadville Public Library are both rich sources of information. Once you have that information you can walk around the towns today and see abundant evidence of what existed over a century ago. The joy of prototyping is learning in great detail how a railroad (and its environs) used to be, or how it is today, and recreating that in minature.

  2. Freelance

    If you choose to invent your own railroad to model -- or perhaps a fictional division of an existing railroad -- you are "freelancing". Prototype modeling has gained a certain snob appeal amongst the model railroad elders in recent years, which is unfortunate because a great freelance road like the Utah Belt is as fascinating as a great prototype model railroad.

    For me, the joy of freelancing is similar to that of the joy of playing a "God" PC game like Sim City or Civilization -- only in far greater detail than any PC game could model. You are in effect the founder and owner of a railroad and its setting, and you can make the decisions as to how it evolved up to the era you are modeling. Of course, the more realistic your assumptions and constraints are, the more interesting your design challenges will be and the more realistic your result will be.

    So, when I started the preliminary designs for my N scale layout a year or so before we moved into this house, I recalled one of my favorite map-drawing scenarios from years earlier. In this scenario a town is founded on a central north-south river (usually, but not always, the Mississippi) in the central U.S. in the mid 19th century. A common occurance, only in this scenario the town leaders are unusually wise, plus a bit wealthier than average. The leaders choose to attract railroads to their town using the lure of a link with the river traffic plus a ready-built bridge across the wide river. From that point forward the town progresses to become a hub city in the transcontinental railroad network with only one difference: the city planners (me) have a bit more foresight than usual.

    This became the basis for the history of my current N scale layout. And although the layout is set in the present era, every single scene on the layout includes evidence of the history of the city and the railroad over the past 150 years.

Maps and railroads -- they seem to go together.

Sunday, March 15, 2009

Making sawdust

Sometimes it seems my main output while building wooden benchwork is sawdust. I used to really like the benchwork part of the hobby, but after a few layouts it has become a drag. Fortunately, I'm almost done with lower deck staging and the main layout uses mostly foam-based benchwork.

So here's where I am tonight:


The subroadbed for the upper tier staging is now completely in place -- and if you look closely you may notice that I put down 9' of additional track next to the wall, too. You can also see the plywood for the middle and lower tiers cut and laying roughly in place -- they were put there temporarily to see that they fit, but they'll be set aside until the upper tier is complete.

Speaking of that, my next task will be to put roadbed and track down for the rest of the upper tier, including connecting to the main layout. I'm looking forward to seeing how trains do with the upper tier slopes.

Once that's in place I'll probably build the power cabinet. Once the staging track is connected to the main layout track it will no longer be practical to test track with just a DC power pack and alligator clips -- I'll need to fully set up the power wiring, including auto reverse devices. So, it makes sense to build the cabinet for those power devices before setting up the devices.

Saturday, March 14, 2009

First Alcove bridge

As I mentioned yesterday I need to build bridges across the west alcove. Three, in fact (one per tier). The first one, for the upper tier, is complete:



1/2" plywood is sufficiently strong to hold N scale trains, the problem is that it will tend to bend and warp without supports (piers) every 12" or so. But the alcove span is 3'9" and I didn't want to build a support grid underneath because I wanted to permit maintenance access to the helix that will later be built in the alcove.

The solution is to use steel L-girders to force the plywood to stay stiff and level. Two L-girders are attached together using nut/bolt/washers and short (1/2") screws with a very wide head are used to attach the L-girders to the plywood. The plywood is supported at both ends by wooden piers. Once constructed test that it is level and adjust as needed (thin plastic shims may prove useful here).

This particular segment of plywood subroadbed was more interesting than usual because on the left side you can (sort of) see that the subroadbed divides into three parts, each with its own grade. I've mentioned this design element briefly in previous posts, but after this section is complete I'll add better photos and describe it in detail.

Friday, March 13, 2009

Design influences: second layout

Model railroading is a lifelong hobby, so they say, but for some reason most of us forget about it during our teens and twenties. We love trains as kids and again after we settle down, but almost every model railroader admits that the lure of girls, cars, and rock n' roll overwhelmed any interest in trains while we were young adults.

So it would have been for me except that my college was on the 4-1-4 system, in which a 1 month "winter term" was sandwiched between two normal 4 month semesters. We had great freedom in choosing our winter term project, and as a freshman I chose to build a model railroad.

I still had no idea about layout design, so on my first trip to the hobby ship I was referred to this layout book:


This was first published in 1956 and is still available today after 30 or 40 printings. Except for the reference to N scale it's basically unchanged from the original version.

Now, the author was Linn Westcott and as I said earlier he was from the old school of layout designers. In his philosophy scenery and realistic views took a back seat to cramming in as much track as possible. Still, he did include a few plans from other designers who tried to create plausible-looking layouts, and I eventually chose this one:

It's not evident until you study it closely, but what makes this layout work is that there is a yard on the left side, then on the right side the railroad climbs up a mountain through a series of switchbacks. The switchbacks add the air of plausibility to the setting -- clearly this railroad had to have tracks close together in order to climb up difficult mountain terrain. The theme is logging/mining, which coincidentally was the theme I'd chosen for this project (trying to justify it as an educational activity for my college).

I modified the plan slightly, reducing the length by 6" to fit into a bedroom and the width from 5' to 4' by reducing the yard at the bottom (it did seem like a huge yard for an otherwise small railroad, I rationalized).

I also knew nothing about construction but I got Westcott's book on model railroad benchwork (an updated version is still available today) and using his "cookie cutter" technique I dived into the building process. I made some mistakes but did get the structure built with a 2x4 gridwork and 1/2" plywood. Then I laid cork roadbed and track. I got so far as to build some kit cars (Colorado Midland -- this was standard gauge as I felt I wasn't ready to tackle narrow gauge just yet), some Campbell wooden structures, and even scratchbuilt a trestle bridge that supported two adjoining tracks -- I was pretty proud of that. I got started creating the base for the mountains when winter term ended and I went back to college (and got credit for the project). All in all a good learning experience.

Once again, alas, my parents moved shortly after the layout was built and only the train materials were saved -- the wood was dismantled and junked.

The main lessons I took to the next layout:
  1. On the plus side, the use of mountains and switchbacks is a good way to create realism while still fitting in a lot of track in a small place. This is because the train still goes "somewhere" vertically, if not so far horizontally. I would use variations of this mountain railroad theme on my next two layouts.

  2. On the minus side, operations that involves short distances of back-and-forth aren't so much fun, at least for me. I prefer relatively long runs. As a result I've never again created this kind of back-and-forth switchback layout, nor the similar industrial switching puzzle kind of layout.

  3. Remember my comments before about loving passenger trains? Yeah, I missed those on this layout. I ran some mixed trains but it wasn't the same. All my subsequent layouts have had passenger trains as a central feature.

  4. Some model railroaders live for steam, and this layout was based in the steam era in part because I was looking forward to running steam. However, I was born in the diesel era and I learned that for me steam is fun but not any more fun than diesel. Since building this layout I've usually had some steam for novelty sake but not as the main theme. Electric, on the other hand, is fascinating ... but that's for discussion of my third layout.

  5. And, of course, I learned that layouts have to be movable. Not exactly "portable", which implies the ability to be transported and set up within a short time, but at least the ability to pack and move to a location thousands of miles away. Every layout that I built after this one had moveability features designed in.
After this layout I did box up and keep the HO equipment I had for many years without ever using it. My next layout wouldn't be started until 9 years later.

More wiring


At first glance this may appear to be a mirror image of the picture from Sunday's post, but this is taken from the other side of the wall. The red/black Power District bus and terminals are complete through this section of staging, and the 3 blue/yellow Auto Reverse (AR) busses have been set up. In addition, the subroadbed for the upper tier track near the wall has been extended through the "window".

I'm now measuring and cutting the rest of the plywood subroadbed, while also working on laying road bed and track for the rear of the upper tier.

Looking at the photo one may wonder why the grid benchwork for staging ends so abruptly. If you refer back to my early post introducing this layout you'll see that there is a small alcove on the middle of this west wall, and that this will be the location of the helix that connects between the two decks. This picture is taken from a spot just next to that alcove, at the top of the stairs. The grid benchwork ends here, and a bridge will be built to connect this track to the track along the west wall on other side of the alcove. I'll post on the building of the bridge later, but fortunately I'll be reusing the bridge method I used with the first staging attempt, so it should go fairly quickly.

Monday, March 9, 2009

Wiring standards part 2: Amendment

One minor addition to the Wiring standards part 2: Terminals and Feeders post: The terminals will always have the black wire connections on left side, red on right side.

Why? Just because.

Sunday, March 8, 2009

North Staging Progress

I now have all the piers in place for the north part of Lower Deck staging, and have the power district terminals and wiring partially in place, as shown here:



My next step is to complete the power district wiring, and then to run the buses for the 3 auto reverse (AR) sections (you can see some of the yellow/blue AR wire pairs in the photo). Once done with that it will be time for the 1/2" plywood subroadbed -- I got another 4x8 sheet at Home Depot today for the purpose. (Lumber prices, after the last few years of outpacing inflation, have suddenly dropped like a rock. This is logical given that construction demand has all but disappeared, but this means I may want to rethink some of my plans to take advantage of the lower prices.)

I won't go into the detailed process for setting up the piers, but for anyone considering tackling a similar project there are a few things to be aware of before starting:
  1. Model Railroad CAD software can plan the locations of our track down to 1/16th of an inch in 3 dimensions, but expect to make many adjustments tranferring those virtual locations to reality. This is especially true if building along a wall, as I am here, as walls are very rarely straight and, in the case of my garage loft, can skew off center by an inch or more from one end to the other. So you can't rely on the wall as a horizontal reference point. Ditto for the floor as a vertical reference point -- floors are rarely level to the fine accuracy that our CAD software assumes they are. So, when setting up your horizontal measurements use a few local reference points then draw lines to make sure that the track locations you've plotted from different locations line up nicely before doing any actual building. I pencil in the track locations on the girders themselves. Similarly for vertical measurements, always link up to the new part of the layout to the existing layout and adjust levels and grades as needed to compensate.

  2. Levels are your friend. I use 3 levels in the measuring process: A 6+ ft level for assuring piers are consistent (either level or at grade) over a long distance, and also for determining required grades over long distances; a 2 ft level for near distance pier-to-pier alignments; and a 9 inch level for checking that piers are level side-to-side.

  3. Fix mistakes as you make them. Sounds simple, but when you are in the middle of a long process like this (62 individual wood pieces, each cut to size and painstakingly put into exact place, at about 5-6 per hour) it's tempting to ignore a mistake "for now" and press on in hopes of reaching completion sooner. Well, at least it is for me. I really have to force myself to measure fully everything after each new piece is in place and redo it if necessary -- but this practice is time-saving in the long run. Fortunately, after a while of doing repetitive work you get so that your mistakes are rare.

One other point to note has to do with vertical curves. You'll see a reasonable amount of discussion on this topic on layout design forums, but most of the detailed write-ups I've seen use HO scale, and thus often need adaptation for N scale.

For this implementation I'm letting the 1/2" plywood subroadbed provide the smooth spiral transition from level to grade and back again. Doing this does require planning the vertical curve such that the 1'-apart piers will provide the support at the right places in the transition and that the joints in the plywood subroadbed occur only at places where the grade is constant -- since we need continuous plywood throughout the transition to make sure it is smooth.

In the past week this has been my main project. However, I've also done a little bit of work on the planning of the switch automation. More on this in a couple weeks after all the staging track is in place.